A contractor undertook to build, within a year, a café building in Gan Sacker park in Jerusalem, for a fixed price of ILS 5.5 million plus VAT. The building was finished very late, and the developer sued him. On 22 November 2026 the Tel Aviv Magistrates' Court held the contractor responsible for a 169-day delay and ordered him to pay the lost rent, supervision costs, the cost of repairing defects and the VAT the developer could not deduct. Several other heads of damage were dismissed as unproven.
What happened
- The contract was signed on 26 January 2017. The works, including the occupancy permit (Form 4), were due by 9 February 2018.
- From August 2017, the supervisor and the developer sent warning letters about the delays. The contractor gave no substantive answer.
- In March 2018 a settlement set a new date and a ILS 250,000 bonus for finishing on time. That date passed as well.
- On 17 July 2018 the developer removed the contractor from the site and finished the work itself. The occupancy permit was issued on 19 August 2018, and the contractor's ILS 350,000 bank guarantee was called.
The delay was proven, and the contractor did not explain it
Once an owner proves the work was finished late, it is up to the contractor to bring evidence that the delay was not his fault. Here he did not:
- "The real contractor was the subcontractor." Whoever signs the contract is bound by it, even if the work was done by someone without the right contractor classification.
- "The project was bigger than presented." The court-appointed expert found no evidence of this.
- "I was asked to do extra work." No complaint made at the time was produced. In the settlement the contractor had even committed to a new date while already knowing all the works.
- "The electricity company and the site works held things up." The site-works argument was raised for the first time in closing submissions, and neither was backed by evidence.
The expert allowed only a three-week extension, to 2 March 2018. From then until the occupancy permit, 169 days went by: 5 months and 16 days.
Lost rent: according to the lease with the tenant
The building had already been let to a café chain, and the delay pushed back the start of the lease. The court awarded ILS 346,129: four months at ILS 60,000, and one month and 16 days at ILS 70,000 a month, plus indexation and VAT.
Two of the developer's demands were rejected. Compensation was not calculated at ILS 80,000 a month, the rent for a later year, but at what the tenant would have paid during the delay itself. The delay also ended on the date of the occupancy permit, not when the tenant started trading. A further ILS 55,161 was awarded for supervision during the delay.
Defects: even without a chance to repair
The developer did not tell the contractor about the defects or let him repair them, as the contract required. The court held that this does not cancel the right to compensation. It only allows compensation to be limited to what the repair would have cost the contractor himself, if he proves that cost, which he did not. The court therefore awarded ILS 179,548 plus VAT, based on expert reports the contractor did not challenge. A 15% overhead was not awarded, because the contract made it conditional on advance notice to the contractor.
Paid the suppliers instead of the contractor? He still owes you an invoice
During the project the contractor signed assignments of rights, and the developer paid part of the price directly to his suppliers. For ILS 821,911 of these payments it received no tax invoice. The contractor argued that he did not have to invoice money that never passed through his hands.
The court rejected this. The real transaction is between the owner and the contractor, and a payment to a supplier under an assignment counts as payment to the contractor. Without invoices the developer could not deduct the VAT, and the contractor was ordered to pay ILS 139,725. A further claim for corporate tax was rejected for lack of an accounting basis.
What was rejected
- Work not done to specification (ILS 435,500). The developer relied on its own supervisor's affidavit, without an expert opinion. The court's expert noted that such gaps should have been deducted before interim invoices were approved.
- Extra costs of completing the project. No payment was linked to a breach by the contractor.
- Financing costs and the cost of another guarantee. Not proven.
The bottom line
The developer claimed ILS 1,780,098. The four heads of damage accepted come to ILS 720,563, from which the called guarantee of ILS 350,000 is deducted. VAT, indexation and interest will be added to the balance. The contractor will also pay the court expert's fee, the court fee and ILS 100,000 in legal fees.
Tips for anyone commissioning building work
- Record delays in writing, at the time. The warning letters made the difference here.
- Found a defect? Tell the contractor in writing and let him repair it, so your compensation is not cut.
- Deduct work not done to specification before approving an invoice, and keep change orders.
- Paying suppliers under an assignment of rights? Ask the contractor for a tax invoice for every payment.
Judgment: Civil Case (Tel Aviv-Jaffa Magistrates) 16919-06-20, given on 22 November 2026.
This article summarizes a published Israeli court decision in plain language and is not legal advice. Every case depends on its facts. The parties' names have been omitted. This is a first-instance decision and may be appealed.